Next Allington Lock Tide: 6:09PM

Current Stream Status: Caution

Twyfordbridge

4 of 2024 - Twyford Bridge Replacement Works

watch_later 07/02/24

Our contractors will shortly begin works to replace the failing Twyford Bridge in Yalding.

Here’s a summary of the key dates and activities:

  • 19th February: Mobilisation and footpath closure begins. This includes Traffic Management on Hampstead Lane and closure of the canoe launch area.
  • 26th February: Floating plant mobilisation starts.
  • 1st March: The floating plant is to be positioned in front of Twyford Bridge Marina.
  • 4th March: Demolition works begin.
  • TBC – Completion

 

The short-term moorings at Yalding will be unavailable during these works. These works should not impede navigation or affect use of the Lifting Bridge at Yalding.

Please note that these dates are subject to change.

Related

River Status

warning_amber

River levels and flows above normal

Environment agency: 03708 506 506



Last updated: 21 Dec, 22:10 PM