22 of 2023 – Winter Draw Down Programme

watch_later 19/12/23

Please see proposed dates for the 2024 Draw down of the Upper River Medway, all dates are weather dependant and may be changed for operational reasons.

05/02/2024

Draw Down

Sluice Weir to Oak Weir

12/02/2024

Draw Down

Oak Weir to East Lock

16/02/2024

Re-Instate

Sluice Weir to Oak Weir

19/02/2024

Draw Down

East Lock to Porters Lock

23/02/2024

Re-Instate

Oak Weir to East Lock

26/02/2024

Draw Down

Porters Lock to Eldridges Lock

01/03/2024

Re-Instate

East Lock to Porters Lock

04/03/2024

Draw Down

Eldridges Lock to Tonbridge Town Lock

08/03/2024

Re-Instate

Porters Lock to Eldridges Lock

11/03/2024

Draw Down

Tonbridge Town Lock to Leigh Flood Storage Area

15/03/2024

Re-Instate

Eldridges Lock to Tonbridge Town Lock

22/03/2024

Re-Instate

Tonbridge Town Lock to Leigh Flood Storage Area

Hampstead Lock to Sluice Weir may be lowered to allow enabling works on the bridge replacement project at Twyford, an update will be issued if this is necessary.

Tonbridge Town Lock to Leigh Flood Storage Area may remain drained for a longer period to enable Tonbridge & Malling Borough Council to conduct essential revetment works at the sports field; dates to be confirmed.